In late September, northeast winds gusting to 50 mph scoured Ocean City's beach for most of a weekend, washed out the dune fencing and left sheer drops where beach-access paths used to slope down to the sand. Most of that sand is sitting just offshore, and this winter the town gets it back in two ways at once. Waves and tides will push some of it home on their own, and the U.S. Army Corps of Engineers will pump in close to a million cubic yards more from Weaver Shoal, more than seven miles out.
Where the Sand Went
The storm started on a Friday. According to OC Today-Dispatch's account of the cleanup, the weather was bad enough that C3 Presents canceled the Oceans Calling Festival less than 24 hours before it was due to start. The following Monday, City Manager Terry McGean, City Engineer Brad Parks and Council President Matt James toured the town from the air with the Maryland State Police Aviation Command.
McGean summed it up for the paper this way: "We experienced significant beach erosion and dune damage, however we had no dune breaches and no flooding from the ocean side." A photo Parks took from the air at 118th Street that day shows a jetty with the sand stripped from around it and a sandbar standing dry at low tide.
That sandbar is where the missing beach went. Parks told OC Today-Dispatch that "a nice sandbar has formed throughout the entirety of OC and offers a layer of shoreline protection offshore." He was just as clear about what the storm left on land: "a lot of scattered debris from dune fencing, a clear loss of dune area and beach access paths that are hazardous with cliffs to vehicles and pedestrians alike."
The Corps explains the same process in its September 29 contract announcement:
"During a nor'easter, powerful waves pull sand from the beach and move it just offshore, but this sand is not lost from the system. As calmer weather returns, moderate periodic waves and tidal currents naturally carry the sand from these offshore sandbars back onto the beach, gradually rebuilding it. Renourishment efforts will supplement this natural process."
Todd M. Beser, USACE Project Manager
So the beach you walk from November to May will be rebuilding itself, slowly, the whole time. The engineered work runs on top of that.
The Corps Was Already on Its Way
The renourishment was booked before the storm hit. Under a 50-year agreement signed in 1994 by Maryland, Worcester County, the Town of Ocean City and the Army Corps, Ocean City's beach usually gets new sand about every four years. The last round finished in 2021. WBOC reported that this project was meant to run last fall and winter, but Congress did not authorize the funding. That makes this the first renourishment in five years.
Because of that delay, the storm landed on a beach that was already overdue, just as the contract was being finalized. The Corps visited Ocean City the Thursday after the storm to assess the damage, and McGean said the contract with the company leading the work would likely need to be amended. The Corps' release says the timing "allows USACE to directly address the recent erosion during the upcoming work."
The contract went to Great Lakes Dredge & Dock Company of Houston for $25.7 million. It covers roughly 982,000 cubic yards of sand to bring the engineered beach berm back to its full design elevation. For comparison, Ocean City Today reported in January 2022 that Weeks Marine pumped 800,000 cubic yards in the 2021 round. The Corps calls the berm "the wide, flat beach in front of the boardwalk and dunes." In other words, it is the stretch of sand most people simply call the beach.
Why the Sand Comes From Seven Miles Out
This round's sand will be dredged at Weaver Shoal, more than seven miles offshore on the Outer Continental Shelf, under an agreement among the Corps, the State of Maryland and the Bureau of Ocean Energy Management. The town has drawn from there before. According to the Corps' 2021 contract announcement, the round finished in December 2017 used up the sand in the designated borrow areas in state waters. The 2021 round then became the first to pump from Weaver Shoal, under a BOEM agreement allowing access to 1.3 million cubic yards of offshore sand for 8.3 miles of beach. This winter is the second trip to the federal shoal. The sand also has to match what is already on the beach.
The cost has gone up sharply. In OC Today-Dispatch's story on the town's autumn capital projects, McGean is quoted telling the City Council that the 2021 project cost $16 million. This one, for "about the same volume of sand," comes to $28 million. The shares are fixed by the 1994 agreement:
- U.S. Army Corps of Engineers: 53%
- State of Maryland: 23.5%
- Worcester County: 11.75%
- Town of Ocean City: 11.75%
The town puts $500,000 a year into a shared fund that earns interest between projects. At this year's price, that wasn't enough. McGean said the local share is now larger than the fund's balance, and the partners had to add millions more. Officials call it "the most important project we do in Ocean City." The Corps estimates the shoreline project has prevented more than $927 million in storm damage since construction started in 1990.
What a Rebuilt Block Looks Like
WBOC described the work in three steps:
- Sand is dredged offshore and sent through a pipeline.
- The pipeline releases it onto the shore.
- Crews shape it along the beach.
During sand placement, crews close the beach three blocks at a time. Ahead of the 2021 round, Ocean City Today described the work area as nearly eight miles of beach between Third Street and just beyond the Maryland-Delaware state line. If the work covers that full length again, a moving three-block closure will pass most of the oceanfront at some point over the winter.
Timing is still loose. In its autumn capital-projects story, OC Today-Dispatch reported that the Corps expected to issue a Notice to Proceed in mid-September, with construction likely starting between mid-October and early November. McGean added that "until the Corp of Engineers holds the project kick-off meeting with the contractor, we won't have a more definitive schedule." The Corps' own September 29 release gives a later window, with beach work starting between late 2026 and early 2027 and finishing before Memorial Day 2027. The last round finished well ahead of its deadline. Weeks Marine wrapped up on December 31, 2021. That was months before the Memorial Day 2022 target the Corps had set.
The Town has set up a Beach Replenishment page with a Project Updates section. For now it reads "Check Back For Updates." It lists Brad Parks and Perry Otwell of Maryland DNR as contacts.
The Boardwalk Gets Longer at the Inlet End
The Boardwalk is due for its own off-season change while the pipeline works the beach. Its south end will be extended east of the Ocean City Life-Saving Station Museum.
The plan started as an elevator. In 2023, the Maryland Department of General Services gave the town $600,000 to add one on the museum's east side so visitors who can't use the stairs could reach the second floor. When bids came in during summer 2024, they ranged from $1.22 million to $1.47 million. In March, the council approved a different plan that uses the $457,436 left in the grant to extend the Boardwalk. That plan adds railings, landscaping and an ADA-compliant interpretive kiosk inside the museum. An archway sign will be paid for with money left over from the Boardwalk signage project.
If bids come in within budget, work could start by December 1, with a goal of finishing by April 1. Public Works Director Hal Adkins said that materials are less of a concern than the calendar: "Being this is simply a 'wood' project I am not overly concerned about any long lead times impacting the schedule on ordering of supplies. More so, I have to work around my 'Special Events Window' of time available to me." The museum stays open on winter weekends, Saturday and Sunday from 10 a.m. to 4 p.m.
The Dates on the Calendar
- After the storm: Parks toured the beach with the Maryland Department of Natural Resources and the Department of General Services to plan debris cleanup and the reopening of several emergency-vehicle access points the storm left inaccessible.
- By December 1: Earliest start for the Boardwalk extension at the museum, if bids come in within budget.
- Late 2026 to early 2027: The Corps' window for pumping sand onto the beach to begin.
- April 1: Target finish for the Boardwalk extension.
- Before Memorial Day 2027: The Corps' deadline for finishing the renourishment.
Every renourishment changes how much beach sits between the dunes and the water, and that is something owners of oceanfront and near-ocean property follow closely from one season to the next. If you hold property along the stretch the pipeline will cover and want to plan the winter around it, Ryan Brant and the Nimble team are tracking the project block by block as it moves. Schedule a Consultation.